Sunday, October 25, 2015

Update: Progress Report (October 25th)

Eric has just returned from a week on the boat where he and DJ were working up forward building the future shop. They accomplished a lot considering that all the aluminum had to be prepped and every piece of insulation and plywood flooring had to be cut to size. Some of the overhead and upper walls still have to be insulated and skinned but will have to wait until the welder repairs the cuts in the forward deck from where the firemen tried to get through. The plywood flooring will have many access points to storage areas underneath. 

At this point in the project, DJ is going to be taking a very needed three week break. He should be back sometime after Thanksgiving. During the Month of September he made a lot of progress on the electrical system and is now wiring systems up under the helm. He was also able to paint several areas as he worked along. One of these areas was under the bunk in the captains' quarters. He's putting in hundreds of hours on work that will be little seen but vital to the function of the ship!











 From This!!!
To This...

To This.... 

To This...
 To the current work shop progress...
What a beautiful transformation!!


DJ painting in the future shop!
Eric cutting plywood flooring for the wood shop!


The main salon is now temporary lumber yard and tool room! 









 More and more piles of pulled, old wire

Behind and under the fridge.
All cleaned up and newly wired.

 Pile of wire pulled from underneath the helm!

 Under the helm.
Newly cleaned and painted

 Ten feet of wire pulled from underneath the helm 
that was wired to the shifters.

Newly shortened shifter cables

 Newly wired shifter

Coat of kilz primer and paint under the bunk!
 

Saturday, September 26, 2015

Update: Progress Report Sept. 26th


DJ is making excellent progress on the electrical system. 
The galley/salon and stateroom sub-panels. 
Currently live but nothing hooked up yet.

The old  32v ac transformer and battery charger. 
DJ has now completely removed the old 32v system.

 This is where the 32v DC system was in the engine room. 
The new bilge pump control panel will go here.

 This is where the 32v battery bank used to be.

 The old 32v battery bank removed from the boat
 and ready for recycling.

 Another pile of old wire, speakers and battery boxes. 

Eric posted this comment on Facebook about the old wiring and why it has been removed:
"Much was so old it had cracked insulation or heavily oxidized copper. Some was house grade not marine grade and not safe to use. Some was just very old, original stuff that had been disconnected and left years ago. On an aluminum boat you don't take chances with electricity.


Monday, September 14, 2015

Update: Progress Report Sept.14th

DJ has spent the month of August and the first two weeks of September pulling more old wire and creating new wire runs and wiring up the new panels in the helm and at the stairwell. He's also been moving water heaters around, inspecting future plumbing projects, removing equipment and getting it off the boat. 
And the most irksome task was a war with fire ants! There had been massive amounts of rain and they decided to invade the boat. He finally won the war but it took about a week or so of spraying. The pictures show dead ants piled up where they kept literally coming out of the wood work. Ugh!!



This was in the galley. DJ pulled the fridge out of the way for a few days so he could work.


Once He is through with this panel he will begin hooking up all the systems.
Beautiful Wiring job! 

 Eric built this panel box the day before we left at the end of our month long work trip in July.





 Everything pictured has now been moved off the boat 
and DJ gave the deck a good scrubbing.

 Fire Ants! Horrible things. 
So glad he got to them before they made it inside.




Sunday, August 2, 2015

Progress Report: Update August 2

The stairwell is transformed! The small locker doors are varnished and will be installed at a later date. Everything has been coated with 2 layers of Kilz primer. We will not be painting this area until after the wood shop is built. We will be having to carry a lot of wood, supplies and tools through here and do not want to risk scraping the final paint job. 



Eric and Mary are now back in Florida and hope to return to the boat soon. DJ is remaining with the boat and will continue with the electrical system and other jobs. 




This was the entrance to the stairwell when we first began working on the boat in March. It was known as 'The Black Hole' and had a powerful smoke smell from the fire damage.

What a difference!

Under the bunk in the captains' cabin has been cleaned and is ready for Kilz primer. The walls still need to be cleaned and scraped, 'cubby' lockers built in, a bench seat added under the window and a few more modifications in the head. 

 The cleaning under the counter and the floor have been finished in the bathroom up forward. Ready for kilz and paint. The flooring is granite tile. The two photos below show the bathroom and head before we started working on the boat in March. Incredible difference!







 DJ's new electrical panel in the lower helm. 
All ready to begin wire connections.


2 A/C units that were in the engine room. They have been removed and sold for funds toward supplies.
DJ pulled the fridge away from the wall in the galley and pulled up more flooring to get to the wiring and plumbing. A lot of this will be removed and simplified. There is a lot of heavy copper tubing under the flooring that will be recycled and the funds used for supplies.

Saturday, July 25, 2015

Progress Report: July 25th

This is the head in the forward area down below, just aft of where the fire started. It was really nasty with black soot and heavy smoke damage. The walls have been scraped and cleaned, ready now for paint prep and Kilz primer. The counter was a dingy green but with a lot of elbow grease, scotch bright pads and GOJO, a beautiful powder blue counter has emerged! We thought the faucet was past saving but both it and the sink cleaned up really nice. These also were done with GOJO. 
   The shower door and stall took about 7 hours. The stall has some staining on the walls and will be painted in future. The toilet was really black but the bowl came out almost pristine. The seat and lid will also be painted in the future.
   Under the counter has been scraped and vacuumed. It, along with two wall lockers have yet to be cleaned. The floor will be cleaned last. The goal is to finish cleaning this bathroom before our work trip is over. 
   The stairwell has a coat of Kilz primer and the top area will be covered with a sheet of door skin. The holes previously had lights in them but we will be covering these up. There is a lip just under the ledge of the locker where a light will be installed at a later date.

We have 3 working days left and will be heading back to Florida on the 30th.